UK’s second subsidy-free solar farm completed by West Sussex Council using battery storage
The UK’s second subsidy-free solar farm, and the first by a local authority using battery storage, has been completed by West Sussex County Council in a project that ticked “every box” and will generate significant income over the next 25 years.
The Westhampnett project combines 7.4MW of solar, comprised of panels from Hanwha Q Cells, with a 4.4MW/4.06MWh battery storage unit from Tesvolt on a closed 35 acre landfill site close to a local grid connection and owned by the council, offering low land costs for the project.
It is the second solar farm to be completed by West Sussex Council following the 5MW Tangmere project, which began operation in October 2015. However, where that site is supported by legacy subsidy payments, Westhampnett has been built purely on the back of an unsubsidised business case.